Yesterday we finished siding the garage west wall, installed the lighting J-block by the garage man door, installed various inside and outside vinyl post corners, J-channels and F-channels, re-leveled the first floor rear master bedroom window, fixed the cut strongback in the first floor trusses, sided half of the east wall of the house, added additional siding on the west wall of the house up to the second window, sided most of the master bedroom south wall, swept, vacuumed, and picked up contractor mess throughout the house, picked up nails around the work site and removed the construction steps. See
http://www.hilliardhabitat.org/Myrtle for some photos from the day.
If the plumber and electrician finish their work early this week, Habitat will call for a framing inspection later this week. If that inspection happens and is passed, then that will allow a number of work items including but not limited to installing Smart Trim on the front and back porches, hanging porch F-channels and soffit, and starting interior insulation.
Regardless, we still have PLENTY of work to do on hanging vinyl siding, wrapping cornices with aluminum, hanging garage and house eave soffit, installing fascia aluminum, and possibly installing conductor lines.
Please RSVP if you plan on joining us, so that we may plan the work day and lunch accordingly. If you can join us on Wednesday, please let Bonnie know by Tuesday morning. (Wednesday volunteers should bring their own lunch). If you can join us on Saturday, please let Bonnie know by Wednesday night (lunch is provided for volunteers on Saturday).Bonnie can be reached at stbrendanhabitat@gmail.com or call or text 614-582-4126.